A 17-story, 420,000 sq ft project. When third-party lab results didn’t match reality, in-place sensor data kept the schedule moving.
Harvey Builders, a general contractor erecting a 17-story building covering 420,000 square feet, ran into a problem that threatened the entire project timeline. Low cylinder break results from a third-party testing lab indicated the concrete did not meet specified strength requirements — setting the project back three weeks.
Third-party lab results showed the concrete was failing to meet specified compressive strength, triggering a three-week delay. The contractor could not proceed with formwork removal or post-tensioning until the discrepancy was resolved. The core question: was the concrete actually underperforming, or were the test results unreliable?
Sensytec deployed 10 SensyCast sensors per floor to track in-place temperature and compressive strength in real time. The sensor data revealed that the concrete met specified strength within just 10 hours of pouring — the third-party lab’s findings did not reflect actual in-place conditions.
Bottom Line
When third-party testing results don’t match what’s happening in the structure, you need an independent source of truth. Sensytec’s sensors gave Harvey Builders the data to prove their concrete met spec, recover a three-week delay, and save $230,000.
The Harvey Builders project demonstrates the value of real-time concrete monitoring on high-rise construction. When traditional testing methods produced unreliable results, Sensytec’s sensors provided the accurate, in-place data needed to keep the project moving.
Harvey Builders saved approximately $230,000 in direct labor and machinery costs and recovered 34 days of project schedule using Sensytec real-time concrete monitoring.
A third-party testing lab reported low cylinder break results, suggesting the concrete failed to meet specified strength. This triggered a three-week delay because formwork couldn’t be stripped and post-tensioning couldn’t proceed.
Sensytec deployed 10 sensors per floor measuring in-place concrete temperature and compressive strength. Within 10 hours of pouring, sensor data showed the concrete had reached specified strength — proving the lab results did not reflect actual conditions.
Real-time strength confirmation enabled 24-hour formwork removal across the project.
The project was a 17-story commercial building covering 420,000 square feet.