Home  /  Case Studies  /  Harvey Builders 17-Story Project
All Case Studies

Harvey Builders: 34 Days Saved, $230K Recovered

A 17-story, 420,000 sq ft project. When third-party lab results didn’t match reality, in-place sensor data kept the schedule moving.

Last updated: April 2026
17-story 420,000 sq ft Harvey Builders construction site using Sensytec sensors at 10 per floor for in-place concrete strength monitoring
Project
17-story, 420,000 sq ft
Industry
General Contractor
Product
10 SensyCast / floor
Lead Result
$230K + 34 days
Key Takeaways
  • 34 days saved across the project schedule
  • $230,000 in direct cost savings (labor + machinery)
  • 24-hour formwork removal cycle achieved
  • 10 sensors per floor across all 17 stories
  • Sensor data proved third-party lab breaks were inaccurate within 10 hours of pour

Introduction

Harvey Builders, a general contractor erecting a 17-story building covering 420,000 square feet, ran into a problem that threatened the entire project timeline. Low cylinder break results from a third-party testing lab indicated the concrete did not meet specified strength requirements — setting the project back three weeks.

The Problem

Third-party lab results showed the concrete was failing to meet specified compressive strength, triggering a three-week delay. The contractor could not proceed with formwork removal or post-tensioning until the discrepancy was resolved. The core question: was the concrete actually underperforming, or were the test results unreliable?

Sensytec’s Solution

Sensytec deployed 10 SensyCast sensors per floor to track in-place temperature and compressive strength in real time. The sensor data revealed that the concrete met specified strength within just 10 hours of pouring — the third-party lab’s findings did not reflect actual in-place conditions.

Key Results

Schedule
34 Days Saved
Project acceleration across remaining floors
Cost Savings
$230,000
Reduced on-site labor and machinery expenses
Formwork
24-hr Removal
Real-time strength confirmation for faster stripping

Bottom Line

When third-party testing results don’t match what’s happening in the structure, you need an independent source of truth. Sensytec’s sensors gave Harvey Builders the data to prove their concrete met spec, recover a three-week delay, and save $230,000.

Conclusion

The Harvey Builders project demonstrates the value of real-time concrete monitoring on high-rise construction. When traditional testing methods produced unreliable results, Sensytec’s sensors provided the accurate, in-place data needed to keep the project moving.

Frequently Asked Questions

How much did Harvey Builders save with Sensytec?

Harvey Builders saved approximately $230,000 in direct labor and machinery costs and recovered 34 days of project schedule using Sensytec real-time concrete monitoring.

What was the original problem on the Harvey Builders project?

A third-party testing lab reported low cylinder break results, suggesting the concrete failed to meet specified strength. This triggered a three-week delay because formwork couldn’t be stripped and post-tensioning couldn’t proceed.

How did Sensytec resolve the testing discrepancy?

Sensytec deployed 10 sensors per floor measuring in-place concrete temperature and compressive strength. Within 10 hours of pouring, sensor data showed the concrete had reached specified strength — proving the lab results did not reflect actual conditions.

How fast was formwork removal with Sensytec data?

Real-time strength confirmation enabled 24-hour formwork removal across the project.

How big was the Harvey Builders project?

The project was a 17-story commercial building covering 420,000 square feet.

Related Case Studies

General Contractor
Skanska: 17-Story Build, Washington DC
DOT
Webber: Texas DOT Highway Construction
Infrastructure
Bush Airport: Runway Repairs, Houston

Want Similar Results?

See how Sensytec can help your operation.

Request a Demo